A Starbucks drive-thru and a self-storage block can be built on the empty Waterloo Avenue site in Fordbridge. It may open 6am to 11pm daily, with 20 jobs.

A Starbucks drive-thru can be built on the empty corner of Cooks Lane and Waterloo Avenue in Fordbridge. Solihull Council granted planning permission in September, and the same scheme adds a three-storey self-storage building behind it.

The decision notice was issued on Friday 18 September. Planning officers decided it themselves rather than sending it to committee, and the register records that it was decided with objections. (Planning register, PL/2026/00545/PPFL)

The 0.51-hectare plot sits at the edge of the Chelmsley Wood Industrial Estate, near the Bacon’s End roundabout. It was once the Bacons End adult training centre. The council was told in 2019 that every structure on it would be demolished, and it has stood empty since. (Demolition notice, PL/2019/02940/PNDEM)

What has been approved

The plans submitted by Burney Estates Development Limited set out:

  • a single-storey drive-thru cafe of 201 square metres, which the application names as a Starbucks
  • a self-storage building of 1,951 square metres, signed in the plans as StoreMore
  • 63 parking spaces, eight of them with electric car chargers and four for blue badge holders
  • a new vehicle entrance, with the site’s old entrances closed off
  • cycle stands outside both buildings

(Planning statement, March 2026)

The application form says the scheme would create 20 full-time jobs. Nobody works on the site now. (Application form)

The conditions neighbours will notice

The permission carries 24 conditions. Three matter most to people living nearby. (Decision notice, 18 September 2026)

  • Opening hours. The drive-thru may serve customers only between 6am and 11pm, seven days a week.
  • A noise wall. Before anything opens, an acoustic barrier at least 2.5 metres high must go up along the western boundary, between the site and the nearest homes.
  • Building work. No work can start until the council has approved a construction plan covering site traffic, contractors’ parking, wheel washing, working hours and a named contact for complaints.

Other conditions cover trees, lighting designed around bats, drainage and contaminated land. Work must start within three years.

How busy it could get

The developer’s transport consultants estimate the whole site would generate 62 car trips in the busiest morning hour, 8am to 9am, counting arrivals and departures. In the evening peak, 5pm to 6pm, the figure is 29. (Transport assessment)

They expect the car park to be fullest at lunchtime, between 12 noon and 1pm, and say 49 spaces would still be free then. These are the applicant’s estimates. A condition requires a travel plan, reviewed twice a year, once the site is in use.

The signs are still undecided

A separate application covers the signs. It includes a 9-metre illuminated totem pole, drive-thru menu boards and a speaker post, illuminated Starbucks logos on the cafe and StoreMore signs on the storage building.

That application had not been decided when we checked the register on 30 October. Its formal consultation ended on 30 April. (Planning register, PL/2026/00546/ADV)

Neither Starbucks nor the developer has announced a building or opening date.

What it means for you

  • If you live on the western side of the site, the 2.5-metre noise barrier and the 11pm closing time are written into the permission. If either is not honoured once it opens, report it to the council’s planning enforcement team via solihull.gov.uk and quote PL/2026/00545/PPFL.
  • If you are worried about the 9-metre lit sign, that decision is still to come. Comments can be made on the register under PL/2026/00546/ADV.
  • If you are looking for work, the application estimates 20 full-time jobs across the cafe and the storage building. No recruitment has been announced.

Other schemes going through the council are on our Solihull planning news page.

Sources: Planning register and documents, PL/2026/00545/PPFL (decision notice, planning statement, application form, transport assessment); Signage application, PL/2026/00546/ADV; Demolition notice, PL/2019/02940/PNDEM.