HS2 will release the first Arden Cross land in 2030. Solihull Cabinet approved a £4.9m bid to plan the site on 12 November, with an outline application due by late 2027.

Overview

Updated 18 November: Cabinet approved the £4.9m bid on 12 November, the draft minutes show. Officers told members they hoped the next report, to accept the grant, would come to Cabinet in February.

HS2 has confirmed that land for the first phase of Arden Cross will be released in 2030. Arden Cross is the planned new district beside the HS2 Interchange station near the NEC. Its developer aims to submit an outline planning application for the whole site by the end of 2027.

The dates are in a report to Solihull Council’s Cabinet for its meeting on Thursday 12 November. Cabinet was asked to approve a bid for £4.9 million of West Midlands Combined Authority grant to plan the site. The council had not published the decision by Friday afternoon.

What Arden Cross could be

The site covers about 140 hectares next to the Interchange station, close to Birmingham Airport and the NEC. The report says the plans identify the potential for:

  • up to 3,000 homes
  • about five million square feet of offices, research and advanced manufacturing space
  • a proposed University of Warwick health technology campus

The report is careful to call these “project aims, not approved delivery outputs”.

The landowners, Arden Cross Limited, appointed the developer Muse as their development partner in December 2024.

Why 2030 matters

Until now the start date has depended on when HS2 hands back land it needs for building the line. The report says HS2’s confirmation of a 2030 release means development “can now be planned to commence with greater certainty”.

Muse can now update the masterplan and planning strategy. It will also work on roads, access and utilities with HS2 and the council. Some enabling work could start before the first buildings, where land access and approvals allow.

What the £4.9 million would pay for

The bid, called a strategic outline case, has two parts:

  • £2.5 million for an outline planning application, the design of roads and infrastructure across the site, and financial modelling. It includes £100,000 for council officers’ time.
  • £2.4 million for more than 50 service ducts and tunnels under the HS2 route. These carry electricity, gas, water and telecoms cables across the line, and must be in place before the track is laid.

The combined authority set aside £50 million for Arden Cross in May 2025, from its City Region Sustainable Transport Settlement. Each part has to be won through a separate business case.

How the money would flow

The grant would be paid to the council, which would pass it to Muse under a funding agreement. The report says no money would reach Muse before that agreement is signed. It says the council would put controls in place so it “does not bear the risks for any project delay or failure”.

A second report would go to Cabinet to accept any grant. This decision does not commit money to building the roads and infrastructure. Any bid for that would need another Cabinet report.

The report lists the main risks as changes to HS2’s land release and programme, planning and funding.

What it means for you

Nothing will be built at Arden Cross before 2030 at the earliest. The next point where residents can have a say is the outline planning application, which Muse aims to submit by the end of 2027. That application would set out how many homes, how much commercial space and which roads the site would have.