The A45 near Bickenhill shuts both ways overnight from 7 December and all weekend from 11 to 14 December, as HS2 moves traffic onto its new bridge.

The A45 Coventry Road near Bickenhill will close in both directions on several nights in December, and for one full weekend. HS2 is moving traffic onto the first half of a new bridge that will carry the road over the railway.

The closures run between Stonebridge Island and Junction 6 of the M42, the stretch past the airport and the NEC. They are set out in HS2’s closure notice for the works, reference HS2-BBV-26-2751.

Overview

The A45 Coventry Road near Bickenhill closes both ways from 9pm to 6am each weeknight from Monday 7 December. It then shuts all weekend, from 9pm on Friday 11 December to 6am on Monday 14 December, before more overnight closures up to Saturday 19 December. Diversions will be signed.

When the A45 is closed

When Hours Which way
Monday 7 to Friday 11 December, each weeknight 9pm to 6am Both directions
Friday 11 to Monday 14 December, full weekend 9pm Friday to 6am Monday Both directions
Monday 14 to Saturday 19 December, each weeknight 9pm to 6am Both directions
Friday 18 to Monday 21 December, only if needed 9pm Friday to 6am Monday Both directions

The last row is a spare weekend. HS2 will use it only if the first weekend’s work is not finished.

The notice itself says the works are “subject to consent”. The dates could still change.

Why the road is closing

HS2 is building a bridge to carry the A45 over the new railway. The line will run in a cutting under the road on its way to Interchange Station, which HS2 says is about a mile away.

The bridge is being built in two halves so that traffic can keep moving. HS2 said on 18 November that the first half was finished. Its announcement gives the scale of the work so far:

  • 46 piles sunk to depths of up to 23 metres
  • 13 pre-stressed concrete beams lifted in over the summer
  • a 37-metre bridge deck weighing 2,000 tonnes when complete
  • 13 parapet units fitted to the first half

The December closures let the contractor, Balfour Beatty VINCI, move the contraflow into a new layout. After that, drivers will use a temporary road alignment that runs over the new eastbound half of the bridge.

Paul Marshall, Head of Delivery at HS2 Ltd, said: “During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we’ll ensure that access to businesses and properties is maintained.”

What comes next

Work on the second half of the bridge starts in the new year, following the same sequence. HS2 expects the bridge to be structurally complete by the end of 2027.

Lighting, kerbs, drainage and the permanent road surface come after that. HS2 says the finished bridge and road layout should be in use by summer 2028.

Under the road, the cutting will carry four tracks into Interchange Station. The station will have two island platforms, each 425 metres long.

What it means for you

  • Plan night journeys between 7 and 19 December. If you drive the A45 between Stonebridge Island and the M42 after 9pm, expect to follow a diversion.
  • The weekend of 11 to 14 December is the big one. The road is shut both ways from Friday night to Monday morning. Allow extra time for any trip to the airport or the NEC that would use this stretch.
  • Diversions will be signed on the day. HS2’s notice does not list the diversion roads, so follow the signs.
  • The Arden Hotel and the fuel station stay open. The notice says both can be reached throughout, and that access to all businesses and homes is kept.
  • Questions go to HS2. Its helpdesk is on freephone 08081 434 434, or email HS2enquiries@hs2.org.uk.